Guide

Condo EV charging:
Ontario, BC and Quebec.

Condo EV charging in Ontario follows Ontario Regulation 48/01: you apply in writing, the board has 60 days to respond, and it can refuse only on a qualified professional's report. In BC, a strata cannot unreasonably refuse a properly made request under section 90.1 of the Strata Property Act. In Quebec, Écorecharge pays up to $5,000 for an individual station in a multi-unit building.

60 days
Ontario board response
3 months
BC strata council decision
$5,000
Quebec individual station, max
Checked November 2026. Programs change often · confirm with the official program page before you buy · MÖTEN evfc does not run any government rebate
Ontario Condos

Ontario: the O. Reg. 48/01 process.

Ontario Regulation 48/01 under the Condominium Act applies to electric vehicle charging systems (EVCS).

  1. Written application

    Signed by the owner, with an address for service, drawings, specifications and installation details. The corporation must help the owner meet these requirements.

  2. Board responds in 60 days

    In writing, unless both sides agree to extend.

  3. Accept, refuse or propose

    Refusal only on a qualified professional's report (law violation, structural integrity, or health and safety). Otherwise accept, or propose an alternative that does not impose unreasonable costs.

  4. Agreement in 90 days

    A written agreement that says who pays installation and ongoing costs.

  5. Registered on title

    The corporation registers it on the unit's title; it takes effect on registration.

Who pays? For an owner-initiated installation, the owner is generally responsible for installation costs unless the agreement says otherwise. When the corporation installs chargers itself, costs are common expenses shared through condo fees. Source: Condominium Authority of Ontario.

Checked November 2026. Programs change; confirm with the official program page before you buy.

BC Strata

BC: what the Strata Property Act allows.

The Government of BC summarizes the EV charging rules for strata corporations as follows.

Owner requests

No unreasonable refusal

A strata corporation cannot unreasonably refuse an owner's request made properly under section 90.1. It can still refuse for reasons such as insufficient electrical capacity. The council must decide within 3 months and can set reasonable conditions, including requiring the owner to pay the costs, in advance if it chooses.

Checked November 2026 · Official source: Gov. of BC
Votes

Majority vote for EV spending

A majority vote, instead of a 3/4 vote, now applies to certain EV charging decisions: contingency reserve fund spending (s. 96), significant changes to common property (s. 71) and related personal property (s. 82). Special levies still need a 3/4 vote.

Checked November 2026 · Official source: Gov. of BC
Electrical planning reports

EPR deadlines

Stratas with five or more lots must obtain an electrical planning report by December 31, 2026 or December 31, 2028, depending on location. The owner-request process applies once the EPR is obtained or its deadline passes; stratas with fewer than five lots follow it as of December 31, 2026.

Checked November 2026 · Official source: Gov. of BC
Rebates

BC Hydro multi-unit funding

EV Ready plan up to $3,000, infrastructure up to $600 per stall ($120,000 per project) and charger rebates up to $14,000 per complex, with pre-approval. Details on our BC incentives page.

Checked November 2026 · Official source: BC Hydro multi-unit rebates

Checked November 2026. Programs change; confirm with the official program page before you buy.

Quebec

Quebec: Écorecharge for residents and syndicates.

Quebec funds both the individual resident and the building. These are the program amounts as of November 2026.

Residents

Individual station

Up to $5,000

For an EV owner living in a multiple dwelling: $600 toward the station plus 50% of eligible installation costs in certain buildings, up to $5,000. The station must be on the eligible list and connected.

Checked November 2026 · Official source: Écorecharge amount
Owners and syndicates

Building projects

Analysis: 75% up to $5,000 per building. Electrical infrastructure: 50% up to $120,000 per building. Stations: $600 per station or per port. Subsidized stations are reserved for residents and their visitors.

Checked November 2026 · Official source: Projects in multiple dwellings · Infrastructure

This guide does not cover Quebec co-ownership (divided co-ownership) rules for charger requests. Ask your syndicate and a Quebec professional. Details on funding: Quebec incentives.

Checked November 2026. Programs change; confirm with the official program page before you buy.

Billing Residents

Charging residents for electricity.

If the building pays for the electricity, it will want to recover it. Measurement Canada rules decide how you can bill.

Measurement Canada

Time, flat fee or kWh

  • Time-based and flat-fee billing are exempt from the Electricity and Gas Inspection Act at this time
  • kWh billing for Level 1 and Level 2 is allowed under a dispensation for devices in service before January 1, 2028, until December 31, 2029
  • Operators billing by kWh must register as contractors under the EGIA (no cost)
  • The billing method must be clear to the driver at the time of the charge

The Measurement Canada page was last modified in October 2022; check it for updates before you set prices.

Checked November 2026 · Official source: Measurement Canada
eMÖTEN

Billing tools on MÖTEN chargers

eMÖTEN supports time, session and kWh pricing; kWh billing in Canada follows Measurement Canada rules. On MÖTEN chargers the CMS subscription is $0, and chargers are OCPP 1.6, 2.0.1 ready.

Capacity

Share capacity with an EVEMS

An EV energy management system lets more stalls share the building's capacity under Rule 8-106 of the Canadian Electrical Code. See the installation guide.

Checked November 2026 · Official source: TSBC bulletin IB-EL 2023-05

Checked November 2026. Programs change; confirm with the official program page before you buy.

Frequently Asked

Condo and strata questions.

Can my condo board refuse an EV charger in Ontario?
Only on limited grounds. Under Ontario Regulation 48/01, the board can refuse only if a qualified professional's report shows the installation would violate the law, compromise the property's structural integrity or create a health and safety risk. It must give you a copy of that report.
How long does an Ontario condo board have to respond?
The corporation has 60 days to respond in writing after you submit a complete application, unless you both agree to extend. If it accepts, you have 90 days to sign a written agreement, which is registered on your unit's title.
Who pays for a condo EV charger in Ontario?
For an owner-initiated installation, the owner is generally responsible for installation costs unless the written agreement says otherwise. When the corporation installs chargers itself, the costs are common expenses shared through condo fees.
Can a BC strata refuse an EV charger?
A strata corporation cannot unreasonably refuse an owner's request made properly under section 90.1 of the Strata Property Act, but it can refuse for reasons such as insufficient electrical capacity. The council must decide within 3 months and can require the owner to pay the costs.
What vote does a BC strata need for EV charging?
A majority vote now applies to certain EV charging decisions, including contingency reserve fund spending and significant changes to common property. Special levies, including those for EV charging infrastructure, still need a 3/4 vote.
Can a condo or strata bill residents per kWh?
Yes, under conditions. Measurement Canada allows kWh billing for Level 1 and Level 2 chargers put into service before January 1, 2028, until December 31, 2029, if the operator registers as a contractor under the Electricity and Gas Inspection Act. Time-based and flat-fee billing are currently exempt.
Are there rebates for condo and strata charging?
In BC and Quebec, yes. BC Hydro funds EV Ready plans, infrastructure and chargers in buildings with five or more units, with pre-approval. Quebec's Écorecharge funds individual stations up to $5,000 and building projects. Ontario has no provincial rebate.

Checked November 2026

Building Projects

Planning charging for your building?

We size the electrical work, plan EVEMS load sharing, and set up eMÖTEN billing for residents. Boards and councils get a written proposal.